Concerning the amount of the claim, the insured has to give us the documents to prove the actual costs incurred for the replacement of medium voltage cabinets and head cutter cables, from which we can determine the amount of the claim is true with the cost needed to replace damaged equipment. We were informed that the insured has chosen to weigh 2 of 2 quotes different contractors before choosing embodiments of contractors' construction company Tien Thanh "cost is VND158,200,000 meet requirements of the insured on the basis of weighing the costs incurred and the progress of repairs. The selection of insured contractors also consider factors minimize the consequences of the loss of business activities affected. We note that the insured has confirmed that no claim for business interruption (number of reference profiles FL000016 compensation). See more discussed our plans for the selection of fix assets in Appendix ...