raw material prices budget (3 kg each): 600the actual materials price: 18,600material price variance = (18,600 x 4)-70,680 = 3720 (favorable)direct materials used = [(6000 x 3)-18600] x 4 = 2400 (not conducive)Actually, we can see that: the right price > 0, so that it exceeded the budget. May be due to the following causes:-Market fluctuations by the price of the material.-Buy in lots which are the substandard products.-For the purchase from the supplier are in adverse condition but the results leave arise additional costs of the transportation industry -During the transportation of the material being shrinkage or excessive damage has arisen.-Do not have the document according to the plan, alternative materials is required to be purchased.